Oracle sends force majeure notice on its New Mexico Stargate data center
The notice would allow Oracle to delay payments should the facility miss its 2028 target to come online.
Via TechCrunch

Oracle has sent a force majeure notice to the developer of Project Jupiter, a Stargate data center campus in New Mexico, Bloomberg first reported Thursday.
Force majeure clauses, common in energy and commodities contracts, excuse a party from contractual obligations when events outside its control get in the way. Oracle is not seeking to exit as the campus’s main tenant, according to Bloomberg’s sources. Instead, the notice would allow the company to delay payments should the facility miss its 2028…
Courtesy
This story was originally published by TechCrunch. All rights belong to the original publisher.
Read the original on techcrunch.com ↗