Microsoft scraps tens-of-billions Texas AI deal with Nscale

Microsoft has walked away from an option to double its AI computing rental at Nscale’s Texas data centre—a deal that could have been worth tens of billions of dollars. The move lands just months before Nscale files for its September 2026 IPO and follows Microsoft’s recent exit from a flagship UK data-centre project after grid delays pushed power supply into the 2030s.

Editor, Lazyfounder

Published 4 min read
Microsoft scraps tens-of-billions Texas AI deal with Nscale
Image: The Next Web via source

30 SEC SUMMARY

  • Microsoft walked away from a deal that could have grown its AI computing rental from Nscale by tens of billions of dollars, just months before the startup’s planned IPO.
  • Nscale lost a second major Microsoft project in Texas after grid delays forced Microsoft to abandon a UK data centre in Essex.
  • Nscale still supplies Microsoft with 200,000 Nvidia GB300 chips under a 2025 contract, but the expansion phase in Texas is now scrapped.
  • The London-based startup recently raised $3.36bn in a pre-IPO round and is pursuing a separate $45bn deal with Anthropic.

KEY HIGHLIGHTS

  • Microsoft opted not to expand its AI computing rental from Nscale in Barstow, Texas, killing a potential deal worth tens of billions.
  • The Texas pull-out follows Microsoft’s October 2026 exit from Nscale’s Essex data-centre project after grid delays pushed power supply into the 2030s.
  • Nscale still supplies Microsoft with roughly 200,000 Nvidia GB300 chips across US and European sites under a 2025 agreement.
  • The London-based AI cloud startup aims for a $35bn valuation in its September 2026 New York IPO and just closed a $3.36bn pre-IPO round.
  • Nscale is negotiating a separate $45bn computing-power deal with Anthropic.

Microsoft kills Texas expansion

Microsoft has spurned an option to more than double the AI computing capacity it rents from Nscale in Barstow, Texas. Had it gone ahead, the deal could have pumped tens of billions of dollars into the London-based startup. The decision landed months before Nscale’s planned September 2026 IPO filing, according to reports in The Next Web and ET Tech.

Under an October 2025 contract, Nscale is already on the hook to ship roughly 200,000 Nvidia GB300 chips to Microsoft sites across the US and Europe. Texas was earmarked as the crown jewel: 104,000 chips starting in Q3 2026, with Microsoft holding a second-phase option for another 700-megawatt campus from late 2027. That option is now dead.

Grid delays dog UK project, Texas expansion scrapped

This is the second time in less than a year that Microsoft has walked away from a major Nscale build. In October 2026 it bailed on anchoring the UK’s largest AI data centre in Loughton, Essex. Grid delays meant power would not arrive until the 2030s—too late for a company racing to train models. Aker chief executive Øyvind Eriksen downplayed the loss, calling the Essex project a "minor contract" in Nscale’s wider book.

Both pull-outs trace back to infrastructure hang-ups. In Texas, the holdup was not grid power but Microsoft’s appetite to commit another 700 megawatts. Critics say the repeated exits expose a pattern: Nscale’s timetables clash with the sprint pace of frontier AI labs.

IPO looms, Anthropic talks heat up

Nscale still has a live October 2025 contract worth tens of billions in total value, but its IPO narrative now leans harder on new customers. The company is chasing a $45bn computing-power deal with Anthropic and closed a $3.36bn pre-IPO round before filing for a New York float aiming for a $35bn valuation.

Nvidia and Norwegian conglomerate Aker are anchor backers, giving Nscale a deep balance sheet. Yet with two headline Microsoft deals now off the table, investors will ask how much of the remaining contracted revenue is truly locked in.

What this means

Lazyfounder analysis — our interpretation, not reported fact.

Microsoft’s rejection removes a blockbuster revenue stream just as Nscale prepares to pitch public investors, raising the stakes for its remaining customer talks—especially the $45bn Anthropic negotiation.

Key takeaways

  • Microsoft’s decision to skip the Texas expansion wipes tens of billions in potential future revenue off Nscale’s IPO projections.
  • Both Microsoft pull-outs—Texas and Essex—stem from infrastructure delays, showing how grid and power risks shape cloud deals.
  • Nscale is racing to lock in alternate customers like Anthropic to offset the lost Microsoft biz before its September 2026 listing.
  • Aker’s Øyvind Eriksen calls the UK exit a 'minor contract,' but two high-value walk-backs in quick succession weaken Nscale’s narrative of rapid scale.

Sources

  1. The Next Web · 2026-11-05
    Microsoft reportedly rejects option to expand Nscale’s Texas AI deal
  2. ET Tech (The Economic Times) · 2026-11-05
    Microsoft rejects multibillion-dollar AI deal with UK's Nscale

This story is an original summary drafted with AI by Lazyfounder from the reporting listed above and checked by automated validation. Facts are attributed to their original publishers; sections marked as analysis are Lazyfounder's. Where a source is in another language, facts were machine-translated and quotations are reported, not reproduced. Read the original coverage via the links, and see our AI policy and corrections policy.

About the author

Editor, Lazyfounder

Tarun Mottlia edits LazyFounders, covering Indian startups, funding rounds, AI and product launches. Every story on the site is AI-assisted and checked against its cited sources before publication.

More stories by Tarun Mottlia

Get the LazyFounder Brief

Startup, funding and AI news in a five-minute read. Join the early-access list.

Lazy Founder - Powered by Blogy.in

Contact us

Have a story tip, correction or partnership idea?

Write to us at tarun.kumar@blogy.in or talk to the founder directly. We read every message.

Contact us